Adsorption, desorption and major overhaul of saturated and unsaturated pools located at the processing factory in Chovdar Ore site
Client name
AzerGold CJSC
Work done
Laying of geomembrane and geogrid layer and carrying out appropriate tests
Project location
Dashkasan region
Project date
2020
Project of adsorption, desorption and major overhaul of saturated and unsaturated pools located at the processing factory in Chovdar Ore site was taken by the AZCD Group as a performer. The list of assigned works consists of equipping with materials and goods, ensuring the efficient operation of the communication system (electricity, water pipes etc.) as well as taking appropriate measures in case of unfavorable weather conditions for welding.